East 140th Project Limits

PROJECT SPECIFICS

Proposed Improvements Along East 140th Street Include:

  • St. Clair to I-90: Narrow and rehabilitate road by resurfacing pavement and reconstruction of drainage facilities

  • I-90 to Lakeshore: Road width remains the same; rehabilitate road by resurfacing  pavement and reconstruction of drainage facilities

  • Replacing non-compliant ADA ramps and curbs, sidewalks, and drive aprons as needed

  • Waterline replacement from St. Clair to Topeka and North Waterloo to Westropp

  • Waterline Service connections replaced from St. Clair to Westropp

  • Signing and pavement marking upgrades include bike lanes between Coit Road and North Waterloo Road and sharrows south of Coit Road and north of North Waterloo Road (for additional information, see the Lane Configuration tab)

  • Improved pedestrian crossings including installation of rectangular rapid flashing beacons (RRFBs) and ladder style crosswalks at Nell and Argus

  • Removal of flashing signal at Nell and removal of traffic signals at Argus and Jenne 

  • Replacement of approach railing and curb on both sides of the CSX Bridge

  • Patching structural curb under the CSX bridge while maintaining the existing railing 

  • Streetscape enhancement, including tree lawns, bike racks, benches, trash receptacles, trees, and Gateway Features

  • Public Art – Mural north of the CSX Bridge

Construction Schedule:
Design Completed
Bid/Award: March 2023
Construction Starts: May 2023
Construction Completion: October 2024


Estimated Construction
Cost:

$8.63 Million

Project Funding Sources:
Federal Grant Funds
Ohio Publi
c Works Commission
Cleveland Road & 
Bridge Bonds and Public Utilities

 

Council Representatives:
Michael D. Polensek
Council Member Ward 8

Anthony T. Hairston
Council Member Ward 10


Project Organizers
:

bottom of page